A tool which is used to illustrate links between work packages or activities and team members is called _______.
A.
Define Scope Matrix
B.
Responsibility Assignment Matrix
C.
Roles Assignment Matrix
D.
Project Scope and Roles Matrix
Explanation:
B is the correct answer. A tool which is used to illustrate links between work packages or activities and team members is called Responsibility Assignment Matrix