A tool which is used to illustrate links between work packages or activities and team members is cal

A tool which is used to illustrate links between work packages or activities and team members is called _______.

A.
Define Scope Matrix

B.
Responsibility Assignment Matrix

C.
Roles Assignment Matrix

D.
Project Scope and Roles Matrix

Explanation:
B is the correct answer. A tool which is used to illustrate links between work packages or activities and team members is called Responsibility Assignment Matrix