A technique showing Kanban work stages by comparing counted features over a time interval is called

A technique showing Kanban work stages by comparing counted features over a time
interval is called a/an:

A.
Earned value system.

B.
Fully integrated backlog.

C.
Cumulative flow diagram.

D.
Progressive elaboration.