A risk response strategy in which the project team shifts the impact of a threat, together with owne seenagape 10 years ago A risk response strategy in which the project team shifts the impact of a threat, together withownership of the response, to a third party is called: A.mitigate B.accept C.transfer D.avoid ← Previous question Next question →