A risk response strategy in which the project team shifts the impact of a threat, together with owne seenagape 8 years ago A risk response strategy in which the project team shifts the impact of a threat,together with ownership of the response, to a third party is called: A. mitigate B. accept C. transfer D. avoid ← Previous question Next question →