A project management professional can compare earned value performance data to all of the following

A project management professional can compare earned value performance data to all of the following project management tools EXCEPT:

A.
Critical path analysis

B.
Technical performance metrics

C.
Risk mitigation plans

D.
Forecasted final costs and schedule estimates