PMI Exam Questions

A project in which the scope, time, and cost of delivery are determined as early as possible is foll

A project in which the scope, time, and cost of delivery are determined as early as
possible is following a life cycle that is:

A.
Adaptive

B.
Predictive

C.
Incremental

D.
Iterative