A project Control Scope system is documented during which of the Project Scope Management processes?

A project Control Scope system is documented during which of the Project Scope Management processes?

A.
Collect Requirements

B.
Define Scope

C.
Verify ScoPe

D.
Control Scope

Explanation:
A project scope management plan should document the Control Scope system.