A major assumption of all network scheduling methods is that the activity duration must be _____. seenagape 8 years ago A major assumption of all network scheduling methods is that the activity duration must be _____. A.Statistically dependent B.Variance distributed C.Statistically independent D.Deterministic ← Previous question Next question →