A logical relationship in which a successor activity cannot start until a predecessor activity has f seenagape 10 years ago A logical relationship in which a successor activity cannot start until a predecessor activity hasfinished is known as: A.Start-to-start (SS). B.Start-to-finish (SF). C.Finish-to-start (FS). D.Finish-to-finish (FF). ← Previous question Next question →