A logical relationship in which a successor activity cannot start until a predecessor activity has f seenagape 9 years ago A logical relationship in which a successor activity cannot start until a predecessoractivity has finished is known as: A. Start-to-start (SS). B. Start-to-finish (SF). C. Finish-to-start (FS). D. Finish-to-finish (FF). ← Previous question Next question →