A document or tool which describes when and how human resources will be brought onto and taken off the project team is called _______.
A.
Staffing Management Plan
B.
Responsibility Assignment Matrix (RAM)
C.
Organizational Breakdown Structure (OBS)
D.
Resource Assignment Chart
Explanation:
Staffing Management Plan :A document or tool which describes when and how human resources will be brought onto and taken off the project team