PMI Exam Questions

A contingency plan is executed when _______.

A contingency plan is executed when _______.

A.
A risk is identified

B.
An identified risk occurs

C.
When a workaround is needed

D.
All of the above

Explanation:
A contingency plan is executed when An identified risk occurs