A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25

A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

A.
Parametric

B.
Bottom up.

C.
Budget

D.
Top down.

E.
Definitive.