A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25 admin 11 years ago A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%). A.Parametric B.Bottom up. C.Budget D.Top down. E.Definitive. ← Previous question Next question →