A project manager needs to deliver the project 2 weeks before the planned date
without changing the scope. Which of the following techniques may be applied to
reevaluate the schedule?

A.
What-if scenario analysis
B.
Critical chain method
C.
Schedule crashing
D.
Resource leveling