Which items should be reviewed when planning the physical installation of a new NonStop
system? (Select three.)

A.
Determine if power is a floor or ceiling feed.
B.
Ensure that there is adequate space for all cabinets including service clearances.
C.
Determine if there is 24×7 operations support for the application.
D.
Ensure that appropriate power capacities and connectors are provided.
E.
Ensure there is adequate heating provided to keep the system cool.