HP Exam Questions

where should network administrator resources be placed when considering a solution proposal?

An existing HP customer has over 20 c7000 enclosures with ProLiant blades and Cisco Ethernet
interconnects. The customer needs to double the size of the environments to accommodate a rise
in computing resource demands. The network administrator workload currently exceeds what can
be accomplished with present staffing, Funding is not available for hiring additional employees.
In a customer SWOT (Strengths, Weaknesses, Opportunities, Threats) analysis, where should
network administrator resources be placed when considering a solution proposal?

A.
Strengths

B.
Opportunities

C.
Weaknesses

D.
Threats

Explanation:
http://www.iu.dk/filer/markedsfoering/tema-arrangementer-1/Session%205%20-%20Swot%20Analysis.pdf(page 9, weaknesses)