When preparing a disaster recovery plan, what would NOT be considered?

PrepAway - Latest Free Exam Questions & Answers

A.
the daily cost of loss if the application is unavailable

B.
the cost of performing the application recovery

C.
the maximum acceptable downtime of the application

D.
the number of end users that are affected by the unavailability