When installing half-height c-Class server blades in a c3000 rack enclosure, what is the
recommended sequence for installing them into the server bays when viewed from the front of the
enclosure?
A.
from top to bottom, then right to left
B.
from bottom to top, then right to left
C.
from top to bottom, then left to right
D.
from bottom to top, then left to right