What is the preferred time for completing the racking and labeling of equipment for a new implementa

What is the preferred time for completing the racking and labeling of equipment for a new
implementation?

A.
At any time between the beginning of the scheduled outage and the point of no return

B.
Before the scheduled outage

C.
At the beginning of the scheduled outage

D.
After the scheduled outage has begun and initial tests have indicated success