Your CloudSystem Matrix environment consists of a single c7000 blade enclosures with 16 blades
and a mix of physical servers and hypervisor hosts. You are asked to provision 40 additional
virtual servers for a two-week project and determine that the CloudSystem Matrix resources are
insufficient. What is the most cost-effective way to add the additional resources to the system?

A.
Add an additional blade server to the existing c7000 enclosures.
B.
Add a VirtualSystem VS1 solution.
C.
Add an existing HP ProLiant server to the extended infrastructure.
D.
Add a CloudSystem Matrix Expansion kit.