Refer to the HP Provision and HP Comware configurations.
An aggregated link has been defined between the Provision A1 and A2 switches, as well as
between the Comware g1/0/1 and g1/0/2 switches. 1 and 2 is not being passed between the
switches. However, during the network administrator’s tests, traffic for VLAN. What is the cause of
this problem?

A.
The PVID on the Comware switch does not match the Provision switch
B.
The VLAN properties need to be defined on A1 and A2 of the Provision switch.
C.
The aggregated link protocol does not match on the two switches
D.
The VLAN properties need to be defined on BAGG1 of the Comware switch
Explanation: