What can be done to allow the DL 170e to be removed for servicing?

A customer has an HP 10642 G2 Rack with Multiple DL2000 servers. The power connection to the
rack is by two full length 7.36 kVA 32A single phase international PDUs with SNMP management
module installed. As shown in the exhibit, the DL 170e servers in the DL2000 chassis are being
blocked in by the PDU.
What can be done to allow the DL 170e to be removed for servicing?

A.
Replace the Existing PDUs with full length, 11kVA 16A 3Phase PDUs.

B.
Replace the existing PDUs with a modular PDU solution.

C.
Replace the existing PDUs with an iPDU Solution.

D.
Mount the existing PDUs upside and feed the power from the top of the rack.