Which drawback presentation?

A company runs a data center for smaller customers. Some of their customers require 24×7
availability, 1 GbEthernet and 4 Gb Fibre Channel networks.
Their SAN consists of a dual redundant fabric with six HP Storage Works 4/32 SAN Switch
in each fabric, The fabrics have a full-mesh topology with two ISLs for each mesh link. They
have only two available freeports on each switch.
The have 20 VMware-based servers and 7 Windows 2008 servers, which are attached with
redundant pathsto their SAN.
They also have three HP EVA 6xxx and two tape libraries with 4 drives of HP Ultrium 4 FC
drives in eachtape library.
Recently they added two HP 3PAR StoreServ 10400 Storage System. The Servers and
storage devices aredistributed on the switches.
All of the devices are distributed between two data centers which are 1 km apart.
The company has not experienced any performance issues.They plan to acquire addition
customer supportfuture growth.
You are asked to present a possible solution to the IT Director of the company.
Which drawback presentation?(Select two)

What is required for heterogeneous implementation?

Your customer wants to implement a high availability connection on their hosts to the local
storage.
They have implemented a multi-vendor firmware issues. The current configuration is as
follows:
Microsoft Windows Server 2008 hosts with 1 QLogic HBA and 1 Emulex HBA
Fabric A contains a Brocade 4/24 port switch.
Fabric B contains a Cisco 9216 with 4 Gb fabric card.
Brocade 1606 routers connect their disaster recovery site.
What is required for heterogeneous implementation?

Which solution will meet the customer requirements?

An existing EVA customer is preparing to deploy HP 3PAR StoreServ 7000 Storage. The
customer previously purchased a par of MPX200 blades for a project, but the blades were
never deployed. The customer wants to migrate data online and require LUN by LUN control
because infrequently used data will be left on the EVA,
Synchronization must be maintained between the EVA and 3PAR LUNs until all a particular
host are migrated.
Which solution will meet the customer requirements?

Which statement is true about this implementation plan?

You are creating and implementation plan with the system engineers for a newly designed
infrastructure solution using HP StoreVirtual 4330 Storage width VMware vSphere. The
proposed backup strategy includesHP Data Protector using the VMware vStorage API for
Data Protection on a native Windows 2008 R2 host. AnHP StoreEver MSL4048 Tape Library
is directly attached to the backup server.
Which statement is true about this implementation plan?

Which SAN infrastructure solution should you recommend in your proposal?

A large customer has a SAN infrastructure with six HP 8/40 SAN switches in each redundant
fabric. To accommodate growing workload’s and expected growth on the SAN, the customer
wants to replace their switches. They also want to reduce associated costs for power,
cooling, and management. The IT Director wants additional capabilities for monitoring and
alerting in the new environment.
Which SAN infrastructure solution should you recommend in your proposal?

Which solution should you recommend to the customer?

A broadcasting company has an aged Fibre Channel-based storage networking
infrastructure. They have three EMC CX-series arrays, each with 50 TB, two HP EVA 8100,
each with 80 TB. They want to update their environments with two new HP 3PAR StoreServ
7400 arrays. Due to their availability requirements, complexity, and the need to avoid
downtime for applications, the company would like to implement online migration using only
proposal.
Which solution should you recommend to the customer?

Which infrastructure purchases should you include in your proposal?

A fast-growing company is planning an acquisition that will add significantly to their customer
base and their data center workload. Environment with 1 Gb Ethernet and 8 Gb Fibre
Channel networks in place. They are open to new technologies and are willing to reduce
cost-effective over time.
Which infrastructure purchases should you include in your proposal?