Which task would successfully resolve this problem?

Click the Exhibit button. An administrator has deployed a two-node cluster with HA and DRS
enabled. DRS has been configured for fully automated mode. The management and
vMotion interfaces have been configured on separate physical networks. Initial DRS testing
on this cluster reveals that virtual machines are not being migrated despite great disparity in
resource use between the ESX hosts in the cluster. The exhibit shows the error and the
network configuration for one of the hosts. Which task would successfully resolve this
problem?

Which two options could be part of the plan to to resolve the issue while minimizing the amount of resources r

Two child resource pools exist for a DRS cluster. The Production resource pool has been

configured with a CPU reservation of 20GHz and a memory reservation of 20GB. The pool
has 16 single-processor virtual machines and 4 dualprocessor virtual machines. Each of
these virtual machines has a CPU reservation of 1GHz and a memory reservation of 1GB.
The Development resource pool and it’s virtual machines have been configured with no
reservations. The pool has 1 single-processor virtual machine and 1 dual-processor virtual
machine. CPU Shares are set to 4000 and Memory Shares are set to 163840. The
Production team members occasionally complain about the performance of their servers.
Which two options could be part of the plan to to resolve the issue while minimizing the
amount of resources reserved by the pool? (Choose two.)

What happens if an ESXi 5.x host that is running the vCenter Server virtual machine experiences a power outage

vCenter Server is running in a virtual machine that is part of a vSphere DRS cluster. The
vCenter Server virtual machine has been tested and can successfully migrate with vMotion
between all ESXi hosts in the cluster. DRS is configured for partial automation. What
happens if an ESXi 5.x host that is running the vCenter Server virtual machine experiences
a power outage?