Exam VCAP5-DCD: VMware Certified Advanced Professional 5 – Data Center Design

The following requirements are stated: RTO: 15 minutes RPO: 15 minutes Uptime: 99.99% The existing vendor rel

You are a VMware architect designing a solution for a client with an existing site who wishes to
build a disaster recovery site. The operations manager has presented some information in the
kickoff meeting. The company has 1,000 VMs, and the average VM has the following specs:
18 GB memory
2 vCPU
100 GB
The company already has an existing vendor relationship with a hardware vendor and would like
to keep the existing storage solution roadmap in place. The following requirements are stated:

RTO: 15 minutes
RPO: 15 minutes
Uptime: 99.99%
The existing vendor relationship is a ______________.

Company B systems can be made available with minimum impact to Company

You are a VMware consultant working at a small managed services company. The company has
won a contract with a large company, Company A, to host its test and dev platform, with the
chance on annual review to host the production platform.
Although you have been engaged early in the project due to business requirements, the budget for
the project has already been combined with that for another DR project for another company,
Company B. The thought process for this decision is that, if needed, the test systems from
Company A have a lower requirement in the unlikely event of Company B having a DR event.
All the items have been bought and are to be delivered. Your role is to take the equipment
provided and construct, develop, and implement a scalable working vSphere platform. The
following requirements are stated:
Company A test machines must be provided with sufficient resources for BAU.
Company B systems can be made available with minimum impact to Company A.
For Company A, RTO is 7 days, and RPO is 1 month.
For company B, RTO is 1 hour, and RPO is 15 minutes.
Using a shared infrastructure in this way is a risk to the project.

Company B systems must be made available with minimum impact to Company

You are a VMware consultant working at a small managed-services company that has won a
contract with a large Company A to host its test and dev platform, with the chance on annual
review to host its production platform.
Although you have been engaged early in the project, because of business requirements, the
budget for the project has already been combined with another DR project for another Company

The thought process for this decision is that, if needed, the test systems from Company A have
a lower requirement in the unlikely event of Company B having a DR event.

All the items have been bought and are to be delivered. Your role is to take the equipment
provided and construct, develop, and implement a scalable working vSphere platform.
The requirements stated are:
Company A test machines must be provided with sufficient resources for BAU.
Company B systems must be made available with minimum impact to Company A.
The RTO for Company A is seven days, with an RPO of one month.
Company B’s RTO is 1 hour, and its RPO is 15 minutes.
The use of a shared infrastructure used in this way is a constraint to the project.

Which of the following discovery methods should be used?

You are a VMware consultant who has been hired to take over a mismanaged VMware vSphere 5
platform estate. You are presented with the vCenter administrator password and given the
following information.
1. The system has full production support from VMware.
2. The platform has been suffering from performance problems for two weeks.
3. No documentation exists.
Your role is to design and implement a platform that meets the following requirements:
R001: Stable for current workloads
R002: Supportable by operations staff
Which of the following discovery methods should be used?

The preferred method for information gathering in this case should be a passive discovery.

You are a VMware consultant who has been hired to take over a mismanaged VMware vSphere 5
platform estate. You are presented with the vCenter administrator password and given the
following information.
The system has full production support from VMware.
The platform has been suffering from performance problems for two weeks.
No documentation exists.
Your role is to design and implement a platform that meets the following requirements:
R001: Stable for current workloads
R002: Supportable by operations staff
The preferred method for information gathering in this case should be a passive discovery.

The performance problem mentioned in the initial project information can be classified as:

You are a VMware consultant who has been hired to take over a mismanaged VMware vSphere 5
platform estate. You are presented with the vCenter administrator password and given the
following information.
The system has full production support from VMware.
The platform has been suffering from performance problems for two weeks.
No documentation exists.
Your role is to design and implement a platform that meets the following requirements:
R001: Stable for current workloads
R002: Supportable by operations staff
The performance problem mentioned in the initial project information can be classified as: