You are VMware designer working at a company where a new business application is being rolled
out. The SLA requirements are RTO of 2 hours and RPO of 10 minutes. During a project team
meeting, the business user misunderstands this requirement. To illustrate the situation, you give
an example where the system becomes unavailable at 4 p.m. To meet the project SLA,
_____________. (Choose two)

which of the following is true?

You are a VMware architect working at a company where a business application is being rolled
out. Based on conversations with the business, you establish that the RTO requirement is 2 hours,
and the RPO requirement is 3 hours. Consider a situation in which the VMware platform is out of
service following multiple hardware issues. The application dropped from service at 2 p.m. To
meet the application business SLA, which of the following is true?