Who carries out checks independent of the project to ensure that the processes are in place for qual seenagape 10 years ago Who carries out checks independent of the project to ensure that the processes are in place forquality planning and control? A.Project Board B.Project Assurance C.Quality Assurance D.Project Support ← Previous question Next question →