PRINCE2 Exam Questions

Who are allowed to raise issues?

Who are allowed to raise issues?

A.
Only the Project Manager and Team Manager

B.
Anyone with an interest in the project or its outcome

C.
Only the Change Authority

D.
Only members of the project management team