PRINCE2 Exam Questions

Which theme has a purpose of providing the mechanisms to forecast the project’s continued via

Which theme has a purpose of providing the mechanisms to forecast the project’s continued

viability?

A.
Risk

B.
Progress

C.
Plans

D.
Business Case