PRINCE2 Exam Questions

Which product should be continuously maintained regarding the status, history and version of a produ

Which product should be continuously maintained regarding the status, history and version of a
product?

A.
Stage Plan

B.
Configuration Item Record

C.
Highlight Report

D.
Product Status Account