PRINCE2 Exam Questions

Which product confirms the version numbers of all products being developed within a given stage?

Which product confirms the version numbers of all products being developed within a given stage?

A.
Configuration Item Record

B.
Stage Plan

C.
Work Package

D.
Product Status Account