Which of the following is NOT a trigger for the project manager to authorize a work package? seenagape 10 years ago Which of the following is NOT a trigger for the project manager to authorize a work package? A. Stage Authorization B. Corrective Action C. Exception plan approved D. Reporting highlights ← Previous question Next question →