PRINCE2 Exam Questions

Which of the following is considered to be an output of a PRINCE2 project?

Which of the following is considered to be an output of a PRINCE2 project?

A.
A measurable improvement to the business

B.
Any tangible or intangible specialist product

C.
A consequence of doing the project that is perceived as negative by one or more stakeholders

D.
The result of change, normally affecting real world behaviour