PRINCE2 Exam Questions

which Management product would the Project Board specify where the authority for change requests lie

In which Management product would the Project Board specify where the authority for change
requests lies?

A.
Risk Management Strategy

B.
Quality Management Strategy

C.
Communication Strategy

D.
Configuration Management Strategy