Which is NOT an objective of the Managing Product Delivery process?

Which is NOT an objective of the Managing Product Delivery process?

A.
Ensures work on products allocated to the team is authorized and agreed

B.
Ensures attention is focused on the delivery of a stage’s products

C.
To send accurate progress information to the Project Manager

D.
Ensures products are delivered to expectations and within tolerance