PRINCE2 Exam Questions

When is the Stage Plan for project initiation produced?

When is the Stage Plan for project initiation produced?

A.
Immediately prior to the authority to deliver a project has been given

B.
Before the Project Board authorize the initiation of the project

C.
After the Project Plan has been produced

D.
During Managing a Stage Boundary process