When is it confirmed if a project’s objectives have been achieved?

When is it confirmed if a project’s objectives have been achieved?

A.
During the Closing a Project process

B.
During the final end stage assessment

C.
During the Controlling a Stage process

D.
During the Managing Product Delivery process