What type of control is a report which is sent from the Team Manager to the Project Manager, at the

What type of control is a report which is sent from the Team Manager to the Project Manager, at
the intervals agreed in the Work Package?

A.
Event-driven

B.
Exception based

C.
Time-driven

D.