What is the purpose of a change budget?
What is the purpose of a change budget?
Which of the following is FALSE regarding the Change theme?
Which of the following is FALSE regarding the Change theme?
Who are allowed to raise an issue?
Who are allowed to raise an issue?
which has now been closed?
Which product would be updated to show that a decision has been made on an off-specification
which has now been closed?
which of the following would be created?
If a product’s weight was specified to be 300 grams but could only be built to a weight of 400
grams, which of the following would be created?
What is a purpose of the Change theme?
What is a purpose of the Change theme?
Which product confirms the version numbers of all products being developed within a given stage?
Which product confirms the version numbers of all products being developed within a given stage?
PRINCE2 uses the term [ ? ] to cover any relevant event that has happened, was not planned, and requires manag
Identify the missing word from the following sentence… PRINCE2 uses the term [ ? ] to cover any
relevant event that has happened, was not planned, and requires management action?
which product can also be used to record required actions or significant events not caught elsewhere?
According to PRINCE2, as well as holding informal problems/concerns, which product can also be
used to record required actions or significant events not caught elsewhere?
Which option describes something that should be provided by the project, but currently is not (or is forecast
Which option describes something that should be provided by the project, but currently is not (or is
forecast not to be) provided?