What statement applies to the Records section?
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality – results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
What statement applies to the Records section?
Which statement applies to the Timing of communication activities section?
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality – results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
Which statement applies to the Timing of communication activities section?
Which statement applies to the Stakeholder analysis: Interested parties section?
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality – results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
Which statement applies to the Stakeholder analysis: Interested parties section?
Which statement applies to the Information needs for each interested party section?
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PID). The PID
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality – results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
Which statement applies to the Information needs for each interested party section?
Which statement is an appropriate entry for the Lessons Log?
Which statement is an appropriate entry for the Lessons Log?
M1ich statement is an appropriate entry for the outline Business Case heading within the Project Brief?
M1ich statement is an appropriate entry for the outline Business Case heading within the Project
Brief?
Which statement is an appropriate entry for the project approach heading within the Project Brief?
Which statement is an appropriate entry for the project approach heading within the Project Brief?
Which statement is an appropriate entry for the Initiation Stage Plan?
Which statement is an appropriate entry for the Initiation Stage Plan?
which of these products will require updating?
During stage 1 the level of performance expected from the service provider was changed.
After this change was agreed which of these products will require updating?
Which fact is an appropriate lesson for the Outsourcing project?
While capturing previous lessons, the Project Manager discovered several interesting facts about
outsourcing.
Which fact is an appropriate lesson for the Outsourcing project?