PRINCE2 Exam Questions

(Note that a collection of related projects being directed to deliver outcomes and benefits related

Please refer to section 1.3 and ‘Programme’ in the Glossary of the PRINCE2 Manual. (Note that a
collection of related projects being directed to deliver outcomes and benefits related to the
organization’s strategic objectives would be a programme NOT a project)

A.
A temporary team that is created to direct and oversee a collection of related projects in order
to deliver outcomes and benefits related to the organization’s strategic objectives

B.
A temporary organization that is created for the purpose of delivering one or more business
products according to an agreed Business Case

C.
A permanent organization that is created for the purpose of realizing one or more business
benefits

D.
A permanent team that is created to deliver a series of business change initiatives