PrepAway - Latest Free Exam Questions & Answers

Category: PRINCE2 Practitioner

Exam PRINCE2 Practitioner: PRINCE2 Practitioner

For each line identify the appropriate option, from options 1 to 6, that applies.

HOTSPOT
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in
part to the increased marketing activities of its competitors. To help counter this, the company has
decided to create a promotional calendar for next year for all its current and prospective
customers. The end product of this project will be a prepared calendar pack, ready for printing.
The design of the calendar will be similar to one sent out previously, and must reflect the company
image as described in the existing corporate branding standards. Another project is currently
producing a new company logo when is to be printed on each page of the promotional calendar.
The prepared calendar pack will consist of:
Design for each month – correctly showing at public holidays and new company logo
Selected photographs- 12 professionally-produced photographs, showing different members of
staff
Selected paper and selected envelope – for printing and mailing the calendar
Chosen label design – a competition to design a label will be held as part of this project
List of customers – names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing departments
Confirm compliance with the Data Protection Legislation
Create a design for each month – this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and
marketing of the calendar is to be produced in stage 2. However, the actual production and
distribution of the calendars is not within the scope of the project. The product cost forecast will be
reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30
November, to enable printing and distribution of the calendar in time for Christmas. The cost of the
activities to develop the specialist products and the cost of the project management activities are
estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost
tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk
budget.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement For each
line identify the appropriate option, from options 1 to 6, that applies. Each option can be used
once, more than once or not at all.

Which 2 statements apply to either the Techniques, processes and procedures or Constraints sections?

Scenario:
Techniques, processes and procedures

1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Which 2 statements apply to either the Techniques, processes and procedures or Constraints
sections?

Which 2 statements apply to either the Reporting arrangements or Problem handling and escalation sections?

Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.

Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Which 2 statements apply to either the Reporting arrangements or Problem handling and
escalation sections?

Which 2 statements apply to either the Extracts or references or Approval method sections?

Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements

8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Which 2 statements apply to either the Extracts or references or Approval method sections?

For each action in Column 1, select from Column 2 the PRINCE2 theme that is being applied.

HOTSPOT
Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Column 1 is a list of actions that occur during the Controlling a Stage process. For each action in
Column 1, select from Column 2 the PRINCE2 theme that is being applied. Each selection from
Column 2 can be used once, more than once or not at all.
Drop down the answer from column 1 to column 2.

complete the transition of the services to the selected service provider.

HOTSPOT
Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
At the end of stage 3, the service provider will be selected and the contract awarded. During stage
4, the Account Manager for the selected service provider will work with the Project Manager to
complete the transition of the services to the selected service provider.


Page 5 of 19« First...34567...10...Last »