NetApp Exam Questions

What must you do to change the operational status to up?

You recently configured your SVM to serve data with the FC protocol by issuing the following commands:
Vserver fcp create -vserver vs1 -status-admin up
Network interface create -vserver vs1 -lif lif1 -role-data -data-protocol fcp –
home-node node_name -home-port port
However, your LIF still shows an operational status of down.
What must you do to change the operational status to up?

A.
License and enable the FC service

B.
Add the LIF to a group

C.
Configure zoning on the switch

D.
Create a LIF on the node’s HA partner

Explanation: