Exam 70-639: TS: Microsoft Office Project Server 2007, Configuring

Which two actions should you perform next? (Each correct answer presents part of the solution

You configure Microsoft Office Project Server 2007 to synchronize with Active Directory on a schedule. You modify the status of a user in the resource pool to be inactive. The following day, you note that the users status is active. You need to ensure that this user remains inactive in the resource pool. You modify the resources properties to set the user as inactive. Which two actions should you perform next? (Each correct answer presents part of the solution. Choose two.)

You need to transfer approval responsibilities for task updates to a different project manager

You are a project manager in your Microsoft Office Project Server 2007 environment. You create and publish a project plan with task assignments. Task progress entries are made through the Project Web Access (PWA) My Tasks page. You need to transfer approval responsibilities for task updates to a different project manager. What should you do?

You need to ensure that users are able to view the most recent project data

In your Microsoft Office Project Server 2007 environment, users report that the Data Analysis views do not include the most recent project data. You configure the PWA cube build settings to use the earliest project start date and the latest project finish date. You successfully rebuild the cube. The recent project data is still not included. You need to ensure that users are able to view the most recent project data. What should you do?

You need to restore the project as quickly as possible to a version that contains the deleted tasks

You enable administrative backups in Microsoft Office Project Server 2007 Project Web Access (PWA). You enable versioning for all projects. A project manager accidentally deletes several tasks from a project that contains thousands of tasks. The project manager then saves and publishes the project. You need to restore the project as quickly as possible to a version that contains the deleted tasks. What should you do?

You need to ensure that the custom fields appear in the field list of the Data Analysis view

You have a Microsoft Office Project Server 2007 environment. You create several custom enterprise project fields and perform the following supporting tasks:

Build the online analysis processing (OLAP) cubes.
Create a Data Analysis view.

Custom fields do not appear in the field list of the Data Analysis view.

You need to ensure that the custom fields appear in the field list of the Data Analysis view.

What should you do?