You need to create a workspace for the new project that meets the following requirements…

Your network environment includes a multi-tier Microsoft Visual Studio Team Foundation Server (TFS) 2012
server implementation. Developers use Visual Studio2012. Your team has just started developing a verylarge
enterprise-scale application. You need to create a workspace for the new project that meets the following
requirements:
· Developers should be able to use Visual Studio 2012 and earlier versions to work with the workspace.
· Performance of the workspace should not be degraded when the number of items in the workspace
increases.
· The storage utilization of the developer local hard drive should be as minimal as possible.
What should you do?

You need to relieve bandwidth by configuring Team Foundation server with the minimal components.What should yo

Your network environment includes two Microsoft Visual Studio Team Foundation Server (TFS) 2012 servers.
A remote site has two teams. Each team uses a different TFS instance. The developers at the remote site
experience poor performance due to network bandwidth issues. You need to relieve bandwidth by configuring
Team Foundation server with the minimal components.What should you do?

You need to provide a solution that prevents check-ins to TFS that will break developers’ builds

Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server.
Your development team has a Visual Studio solution file that is used to build a software product. A developer
reports that when he retrieves the latest source file to his computer from TFS and performs a build, the build
frequently breaks. You need to provide a solution that prevents check-ins to TFS that will break developers’
builds. What should you do?

What are two possible ways to accomplishthis goal?

Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. You
create a new project using the default Visual Studio Scrum 2.0 template. You want to inform the product owner
when a Product Backlog Item (PBI) is ready for testing. You need to ensure that when the development of a
PBI has been completed, the tester is able to change the state of the item to be Ready for Acceptance Testing.
You need to achieve this goal without developing custom code. What are two possible ways to accomplishthis
goal? (Each correct answer presents a complete solution. Choose two.)

You need to meet the following requirements: · The process will stop new builds from being started while

Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server.
Developers use Visual Studio 2012. You want to modify the build definition deployment process.
You need to meet the following requirements:
· The process will stop new builds from being started while making the modifications. · Builds should queue up
while modifications are being made. · Once modifications are complete, all queued builds should be
processed.
What should you do?

You need to connect the Microsoft Exceldocument containing the work items to the new Team Project Collection

You are business analyst. You use MS Excel to add and edit work items of a team project. You store those
work items in an offline worksheet. Recently your team project has been moved to another Team Project
Collection. You need to connect the Microsoft Exceldocument containing the work items to the new Team
Project Collection. What should you do from within Microsoft Excel?

Which three actions should you perform?

Your network environment includes a single Microsoft Visual Studio Team Foundation Server (TFS) 2012
server. You are using the Default Template to builda solution that will be debugged by using IntelliTrace. You
need to ensure that symbols will be available to IntelliTrace for each build. Which three actions should you
perform? (Each correct answer presents part of the solution. Choose three.)

You need to configure a set of build definitions that rely on this software component to utilize the correct b

Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. You
are configuring a set of automated build servers for TFS that includes one build controller and four build
servers, with TFS Build Agents installed on each. All build servers are configured with the same base set of
software. You have a software component that is licensed for a single build server and can be installed on only
one build machine. You need to configure a set of build definitions that rely on this software component to
utilize the correct build machine. What should you do?