PrepAway - Latest Free Exam Questions & Answers

Category: 70-247 (v.4)

Exam 70-247: Configuring and Deploying a Private Cloud with System Center 2012 (update August 07th, 2017)

which System Center 2012 components should you configur…

###BeginCaseStudy###

Testlet 1
Overview
Proseware, Inc. is an international publishing company.
Proseware has four data centers and 80 offices. The data centers are located in Dallas, Dublin, Bangalore, and
Sydney. The offices are located worldwide.
Existing Environment
Network Infrastructure
The network contains a single-domain Active Directory forest named proseware.com.
Each server has a Baseboard Management Controller (BMC) installed.
Database administrators in the Bangalore data center manage all of the SQL Server servers in the data
centers.
Dublin Data Center
The Dublin data center contains two servers. The servers are configured as shown in the following table.

Operations Manager 2007 R2 agents are installed on all of the servers in the Dublin data center by using the
push installation method.
App1
Proseware uses a critical business application named Appl. Multiple instances of App1 are deployed to each
data center.
Each instance of App1 consists of the following physical servers that run Windows Server 2012:
A database server that runs SQL Server 2008 R2.
Two web servers that are load balanced by using the Network Load Balancing (NLB) feature. Each web
server has a single network adapter.
New versions of App1 are released at least four times a year.
When a new version of App1 is released, all of the servers in App1 must be redeployed.
Requirements
Planned Changes
Proseware plans to deploy all System Center 2012 components.
Proseware plans to implement the following changes in each data center:
Deploy a SQL Server 2008 R2 Enterprise failover cluster.Store all virtual machine data in a Fibre Channel SAN infrastructure.
Deploy a highly available Virtual Machine Manager (VMM) environment.
Deploy one physical server that has Data Protection Manager (DPM) deployed.
Technical Requirements
Proseware identifies the following technical requirements for the implementation of a private cloud:
All Hyper-V hosts must be added to a failover cluster automatically.
The deployment of Hyper-V hosts to each data center must be automated.
The implementation of the DPM infrastructure must meet the following requirements:
– Backups will be stored on an iSCSI SAN.
– Virtual machines in a running state must be backed up from their respective host. Administrators must be
able to restore individual files from host backups on virtual machines configured as file servers.
The implementation of the Operations Manager 2012 infrastructure must meet the following requirements:
– Operations Manager monitoring must not be affected if a single server fails.
– Existing data must be retained in the Operations Manager 2012 infrastructure.
– Existing agents must continue to report to Operations Manager during the upgrade process.
– All Operations Manager agents must report to a local management server in their respective data center.
– The service desk in the Dublin data center must be able to view the status of the servers in all of the data
centers.
Administrative Requirements
Proseware identifies the following administrative requirements:
An administrator must be notified when an error occurs on a server.
An administrator must be able to assign errors to specific administrators for resolution.
Errors that remain unresolved for more than 10 hours must be escalated automatically to another
administrator.
Planned Virtual Machines
The servers in each instance of App1 will be replaced with a set of virtual machines. The planned changes
must meet the following requirements:
Each instance must be redeployed when a new version of App1 is released.
Each instance of App1 must be installed by using the minimum amount of administrative effort.
App2
An application named App2 is hosted on the virtual machines in a Windows Azure public cloud infrastructure.
The performance and availability of the components of App2 must be monitored centrally. Administrators must
be able to modify the configurations of the App2 components.
App3
A service template will be used to deploy multiple instances of a multi-tier application named App3. The vendor
of App3 will provide updates to App3 every two months.
SQL Server Deployment Requirements
VMM administrators plan to deploy many virtual machines that have SQL Server deployed. The administrators
identify the following deployment options for the virtual machines:
The virtual machines will host databases that will be created by using data-tier application (DAC) packages.
The virtual machines will have SQL Server 2008 R2 Standard deployed by using one of six different
configurations.
The operating system for the virtual machines will be either Windows Server 2008 R2 Enterprise or
Windows Server 2008 R2 Standard.

###EndCaseStudy###

You need to configure connectors between the System Center 2012 components to meet the administrative
requirements. Between which System Center 2012 components should you configure the connectors?

What should you recommend?

###BeginCaseStudy###

Testlet 1
Overview
Proseware, Inc. is an international publishing company.
Proseware has four data centers and 80 offices. The data centers are located in Dallas, Dublin, Bangalore, and
Sydney. The offices are located worldwide.
Existing Environment
Network Infrastructure
The network contains a single-domain Active Directory forest named proseware.com.
Each server has a Baseboard Management Controller (BMC) installed.
Database administrators in the Bangalore data center manage all of the SQL Server servers in the data
centers.
Dublin Data Center
The Dublin data center contains two servers. The servers are configured as shown in the following table.

Operations Manager 2007 R2 agents are installed on all of the servers in the Dublin data center by using the
push installation method.
App1
Proseware uses a critical business application named Appl. Multiple instances of App1 are deployed to each
data center.
Each instance of App1 consists of the following physical servers that run Windows Server 2012:
A database server that runs SQL Server 2008 R2.
Two web servers that are load balanced by using the Network Load Balancing (NLB) feature. Each web
server has a single network adapter.
New versions of App1 are released at least four times a year.
When a new version of App1 is released, all of the servers in App1 must be redeployed.
Requirements
Planned Changes
Proseware plans to deploy all System Center 2012 components.
Proseware plans to implement the following changes in each data center:
Deploy a SQL Server 2008 R2 Enterprise failover cluster.Store all virtual machine data in a Fibre Channel SAN infrastructure.
Deploy a highly available Virtual Machine Manager (VMM) environment.
Deploy one physical server that has Data Protection Manager (DPM) deployed.
Technical Requirements
Proseware identifies the following technical requirements for the implementation of a private cloud:
All Hyper-V hosts must be added to a failover cluster automatically.
The deployment of Hyper-V hosts to each data center must be automated.
The implementation of the DPM infrastructure must meet the following requirements:
– Backups will be stored on an iSCSI SAN.
– Virtual machines in a running state must be backed up from their respective host. Administrators must be
able to restore individual files from host backups on virtual machines configured as file servers.
The implementation of the Operations Manager 2012 infrastructure must meet the following requirements:
– Operations Manager monitoring must not be affected if a single server fails.
– Existing data must be retained in the Operations Manager 2012 infrastructure.
– Existing agents must continue to report to Operations Manager during the upgrade process.
– All Operations Manager agents must report to a local management server in their respective data center.
– The service desk in the Dublin data center must be able to view the status of the servers in all of the data
centers.
Administrative Requirements
Proseware identifies the following administrative requirements:
An administrator must be notified when an error occurs on a server.
An administrator must be able to assign errors to specific administrators for resolution.
Errors that remain unresolved for more than 10 hours must be escalated automatically to another
administrator.
Planned Virtual Machines
The servers in each instance of App1 will be replaced with a set of virtual machines. The planned changes
must meet the following requirements:
Each instance must be redeployed when a new version of App1 is released.
Each instance of App1 must be installed by using the minimum amount of administrative effort.
App2
An application named App2 is hosted on the virtual machines in a Windows Azure public cloud infrastructure.
The performance and availability of the components of App2 must be monitored centrally. Administrators must
be able to modify the configurations of the App2 components.
App3
A service template will be used to deploy multiple instances of a multi-tier application named App3. The vendor
of App3 will provide updates to App3 every two months.
SQL Server Deployment Requirements
VMM administrators plan to deploy many virtual machines that have SQL Server deployed. The administrators
identify the following deployment options for the virtual machines:
The virtual machines will host databases that will be created by using data-tier application (DAC) packages.
The virtual machines will have SQL Server 2008 R2 Standard deployed by using one of six different
configurations.
The operating system for the virtual machines will be either Windows Server 2008 R2 Enterprise or
Windows Server 2008 R2 Standard.

###EndCaseStudy###

DRAG DROP
You need to recommend a solution to meet the requirements for App2.
What should you recommend? (To answer, drag the appropriate actions to the correct components. Each
action may be used once, more than once, or not at alt. You may need to drag the split bar between panes or
scroll to view content.)
Select and Place:

Which three actions should you perform in sequence?

###BeginCaseStudy###

Testlet 1
Overview
Proseware, Inc. is an international publishing company.
Proseware has four data centers and 80 offices. The data centers are located in Dallas, Dublin, Bangalore, and
Sydney. The offices are located worldwide.
Existing Environment
Network Infrastructure
The network contains a single-domain Active Directory forest named proseware.com.
Each server has a Baseboard Management Controller (BMC) installed.
Database administrators in the Bangalore data center manage all of the SQL Server servers in the data
centers.
Dublin Data Center
The Dublin data center contains two servers. The servers are configured as shown in the following table.

Operations Manager 2007 R2 agents are installed on all of the servers in the Dublin data center by using the
push installation method.
App1
Proseware uses a critical business application named Appl. Multiple instances of App1 are deployed to each
data center.
Each instance of App1 consists of the following physical servers that run Windows Server 2012:
A database server that runs SQL Server 2008 R2.
Two web servers that are load balanced by using the Network Load Balancing (NLB) feature. Each web
server has a single network adapter.
New versions of App1 are released at least four times a year.
When a new version of App1 is released, all of the servers in App1 must be redeployed.
Requirements
Planned Changes
Proseware plans to deploy all System Center 2012 components.
Proseware plans to implement the following changes in each data center:
Deploy a SQL Server 2008 R2 Enterprise failover cluster.Store all virtual machine data in a Fibre Channel SAN infrastructure.
Deploy a highly available Virtual Machine Manager (VMM) environment.
Deploy one physical server that has Data Protection Manager (DPM) deployed.
Technical Requirements
Proseware identifies the following technical requirements for the implementation of a private cloud:
All Hyper-V hosts must be added to a failover cluster automatically.
The deployment of Hyper-V hosts to each data center must be automated.
The implementation of the DPM infrastructure must meet the following requirements:
– Backups will be stored on an iSCSI SAN.
– Virtual machines in a running state must be backed up from their respective host. Administrators must be
able to restore individual files from host backups on virtual machines configured as file servers.
The implementation of the Operations Manager 2012 infrastructure must meet the following requirements:
– Operations Manager monitoring must not be affected if a single server fails.
– Existing data must be retained in the Operations Manager 2012 infrastructure.
– Existing agents must continue to report to Operations Manager during the upgrade process.
– All Operations Manager agents must report to a local management server in their respective data center.
– The service desk in the Dublin data center must be able to view the status of the servers in all of the data
centers.
Administrative Requirements
Proseware identifies the following administrative requirements:
An administrator must be notified when an error occurs on a server.
An administrator must be able to assign errors to specific administrators for resolution.
Errors that remain unresolved for more than 10 hours must be escalated automatically to another
administrator.
Planned Virtual Machines
The servers in each instance of App1 will be replaced with a set of virtual machines. The planned changes
must meet the following requirements:
Each instance must be redeployed when a new version of App1 is released.
Each instance of App1 must be installed by using the minimum amount of administrative effort.
App2
An application named App2 is hosted on the virtual machines in a Windows Azure public cloud infrastructure.
The performance and availability of the components of App2 must be monitored centrally. Administrators must
be able to modify the configurations of the App2 components.
App3
A service template will be used to deploy multiple instances of a multi-tier application named App3. The vendor
of App3 will provide updates to App3 every two months.
SQL Server Deployment Requirements
VMM administrators plan to deploy many virtual machines that have SQL Server deployed. The administrators
identify the following deployment options for the virtual machines:
The virtual machines will host databases that will be created by using data-tier application (DAC) packages.
The virtual machines will have SQL Server 2008 R2 Standard deployed by using one of six different
configurations.
The operating system for the virtual machines will be either Windows Server 2008 R2 Enterprise or
Windows Server 2008 R2 Standard.

###EndCaseStudy###

DRAG DROP
You need to recommend a method to upgrade DublinMG to Operations Manager 2012.
Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the
list of actions to the answer area and arrange them in the correct order.)
Select and Place:

What should you include in the recommendation?

###BeginCaseStudy###

Testlet 1
Overview
Proseware, Inc. is an international publishing company.
Proseware has four data centers and 80 offices. The data centers are located in Dallas, Dublin, Bangalore, and
Sydney. The offices are located worldwide.
Existing Environment
Network Infrastructure
The network contains a single-domain Active Directory forest named proseware.com.
Each server has a Baseboard Management Controller (BMC) installed.
Database administrators in the Bangalore data center manage all of the SQL Server servers in the data
centers.
Dublin Data Center
The Dublin data center contains two servers. The servers are configured as shown in the following table.

Operations Manager 2007 R2 agents are installed on all of the servers in the Dublin data center by using the
push installation method.
App1
Proseware uses a critical business application named Appl. Multiple instances of App1 are deployed to each
data center.
Each instance of App1 consists of the following physical servers that run Windows Server 2012:
A database server that runs SQL Server 2008 R2.
Two web servers that are load balanced by using the Network Load Balancing (NLB) feature. Each web
server has a single network adapter.
New versions of App1 are released at least four times a year.
When a new version of App1 is released, all of the servers in App1 must be redeployed.
Requirements
Planned Changes
Proseware plans to deploy all System Center 2012 components.
Proseware plans to implement the following changes in each data center:
Deploy a SQL Server 2008 R2 Enterprise failover cluster.Store all virtual machine data in a Fibre Channel SAN infrastructure.
Deploy a highly available Virtual Machine Manager (VMM) environment.
Deploy one physical server that has Data Protection Manager (DPM) deployed.
Technical Requirements
Proseware identifies the following technical requirements for the implementation of a private cloud:
All Hyper-V hosts must be added to a failover cluster automatically.
The deployment of Hyper-V hosts to each data center must be automated.
The implementation of the DPM infrastructure must meet the following requirements:
– Backups will be stored on an iSCSI SAN.
– Virtual machines in a running state must be backed up from their respective host. Administrators must be
able to restore individual files from host backups on virtual machines configured as file servers.
The implementation of the Operations Manager 2012 infrastructure must meet the following requirements:
– Operations Manager monitoring must not be affected if a single server fails.
– Existing data must be retained in the Operations Manager 2012 infrastructure.
– Existing agents must continue to report to Operations Manager during the upgrade process.
– All Operations Manager agents must report to a local management server in their respective data center.
– The service desk in the Dublin data center must be able to view the status of the servers in all of the data
centers.
Administrative Requirements
Proseware identifies the following administrative requirements:
An administrator must be notified when an error occurs on a server.
An administrator must be able to assign errors to specific administrators for resolution.
Errors that remain unresolved for more than 10 hours must be escalated automatically to another
administrator.
Planned Virtual Machines
The servers in each instance of App1 will be replaced with a set of virtual machines. The planned changes
must meet the following requirements:
Each instance must be redeployed when a new version of App1 is released.
Each instance of App1 must be installed by using the minimum amount of administrative effort.
App2
An application named App2 is hosted on the virtual machines in a Windows Azure public cloud infrastructure.
The performance and availability of the components of App2 must be monitored centrally. Administrators must
be able to modify the configurations of the App2 components.
App3
A service template will be used to deploy multiple instances of a multi-tier application named App3. The vendor
of App3 will provide updates to App3 every two months.
SQL Server Deployment Requirements
VMM administrators plan to deploy many virtual machines that have SQL Server deployed. The administrators
identify the following deployment options for the virtual machines:
The virtual machines will host databases that will be created by using data-tier application (DAC) packages.
The virtual machines will have SQL Server 2008 R2 Standard deployed by using one of six different
configurations.
The operating system for the virtual machines will be either Windows Server 2008 R2 Enterprise or
Windows Server 2008 R2 Standard.

###EndCaseStudy###

You need to recommend a solution to ensure that the database administrators can install, stop, start, and
remotely control all of the virtual machines that run SQL Server from a single self-service console.
What should you include in the recommendation?

Which configuration or configurations should you recommend?

###BeginCaseStudy###

Testlet 1
Overview
Proseware, Inc. is an international publishing company.
Proseware has four data centers and 80 offices. The data centers are located in Dallas, Dublin, Bangalore, and
Sydney. The offices are located worldwide.
Existing Environment
Network Infrastructure
The network contains a single-domain Active Directory forest named proseware.com.
Each server has a Baseboard Management Controller (BMC) installed.
Database administrators in the Bangalore data center manage all of the SQL Server servers in the data
centers.
Dublin Data Center
The Dublin data center contains two servers. The servers are configured as shown in the following table.

Operations Manager 2007 R2 agents are installed on all of the servers in the Dublin data center by using the
push installation method.
App1
Proseware uses a critical business application named Appl. Multiple instances of App1 are deployed to each
data center.
Each instance of App1 consists of the following physical servers that run Windows Server 2012:
A database server that runs SQL Server 2008 R2.
Two web servers that are load balanced by using the Network Load Balancing (NLB) feature. Each web
server has a single network adapter.
New versions of App1 are released at least four times a year.
When a new version of App1 is released, all of the servers in App1 must be redeployed.
Requirements
Planned Changes
Proseware plans to deploy all System Center 2012 components.
Proseware plans to implement the following changes in each data center:
Deploy a SQL Server 2008 R2 Enterprise failover cluster.Store all virtual machine data in a Fibre Channel SAN infrastructure.
Deploy a highly available Virtual Machine Manager (VMM) environment.
Deploy one physical server that has Data Protection Manager (DPM) deployed.
Technical Requirements
Proseware identifies the following technical requirements for the implementation of a private cloud:
All Hyper-V hosts must be added to a failover cluster automatically.
The deployment of Hyper-V hosts to each data center must be automated.
The implementation of the DPM infrastructure must meet the following requirements:
– Backups will be stored on an iSCSI SAN.
– Virtual machines in a running state must be backed up from their respective host. Administrators must be
able to restore individual files from host backups on virtual machines configured as file servers.
The implementation of the Operations Manager 2012 infrastructure must meet the following requirements:
– Operations Manager monitoring must not be affected if a single server fails.
– Existing data must be retained in the Operations Manager 2012 infrastructure.
– Existing agents must continue to report to Operations Manager during the upgrade process.
– All Operations Manager agents must report to a local management server in their respective data center.
– The service desk in the Dublin data center must be able to view the status of the servers in all of the data
centers.
Administrative Requirements
Proseware identifies the following administrative requirements:
An administrator must be notified when an error occurs on a server.
An administrator must be able to assign errors to specific administrators for resolution.
Errors that remain unresolved for more than 10 hours must be escalated automatically to another
administrator.
Planned Virtual Machines
The servers in each instance of App1 will be replaced with a set of virtual machines. The planned changes
must meet the following requirements:
Each instance must be redeployed when a new version of App1 is released.
Each instance of App1 must be installed by using the minimum amount of administrative effort.
App2
An application named App2 is hosted on the virtual machines in a Windows Azure public cloud infrastructure.
The performance and availability of the components of App2 must be monitored centrally. Administrators must
be able to modify the configurations of the App2 components.
App3
A service template will be used to deploy multiple instances of a multi-tier application named App3. The vendor
of App3 will provide updates to App3 every two months.
SQL Server Deployment Requirements
VMM administrators plan to deploy many virtual machines that have SQL Server deployed. The administrators
identify the following deployment options for the virtual machines:
The virtual machines will host databases that will be created by using data-tier application (DAC) packages.
The virtual machines will have SQL Server 2008 R2 Standard deployed by using one of six different
configurations.
The operating system for the virtual machines will be either Windows Server 2008 R2 Enterprise or
Windows Server 2008 R2 Standard.

###EndCaseStudy###

You need to recommend which network configuration or configurations are required for the virtual web servers
for each instance of App1.
Which configuration or configurations should you recommend? (Each correct answer presents part of the
solution. Choose all that apply.)

What should you include in the recommendation?

###BeginCaseStudy###

Testlet 1
Overview
Proseware, Inc. is an international publishing company.
Proseware has four data centers and 80 offices. The data centers are located in Dallas, Dublin, Bangalore, and
Sydney. The offices are located worldwide.
Existing Environment
Network Infrastructure
The network contains a single-domain Active Directory forest named proseware.com.
Each server has a Baseboard Management Controller (BMC) installed.
Database administrators in the Bangalore data center manage all of the SQL Server servers in the data
centers.
Dublin Data Center
The Dublin data center contains two servers. The servers are configured as shown in the following table.

Operations Manager 2007 R2 agents are installed on all of the servers in the Dublin data center by using the
push installation method.
App1
Proseware uses a critical business application named Appl. Multiple instances of App1 are deployed to each
data center.
Each instance of App1 consists of the following physical servers that run Windows Server 2012:
A database server that runs SQL Server 2008 R2.
Two web servers that are load balanced by using the Network Load Balancing (NLB) feature. Each web
server has a single network adapter.
New versions of App1 are released at least four times a year.
When a new version of App1 is released, all of the servers in App1 must be redeployed.
Requirements
Planned Changes
Proseware plans to deploy all System Center 2012 components.
Proseware plans to implement the following changes in each data center:
Deploy a SQL Server 2008 R2 Enterprise failover cluster.Store all virtual machine data in a Fibre Channel SAN infrastructure.
Deploy a highly available Virtual Machine Manager (VMM) environment.
Deploy one physical server that has Data Protection Manager (DPM) deployed.
Technical Requirements
Proseware identifies the following technical requirements for the implementation of a private cloud:
All Hyper-V hosts must be added to a failover cluster automatically.
The deployment of Hyper-V hosts to each data center must be automated.
The implementation of the DPM infrastructure must meet the following requirements:
– Backups will be stored on an iSCSI SAN.
– Virtual machines in a running state must be backed up from their respective host. Administrators must be
able to restore individual files from host backups on virtual machines configured as file servers.
The implementation of the Operations Manager 2012 infrastructure must meet the following requirements:
– Operations Manager monitoring must not be affected if a single server fails.
– Existing data must be retained in the Operations Manager 2012 infrastructure.
– Existing agents must continue to report to Operations Manager during the upgrade process.
– All Operations Manager agents must report to a local management server in their respective data center.
– The service desk in the Dublin data center must be able to view the status of the servers in all of the data
centers.
Administrative Requirements
Proseware identifies the following administrative requirements:
An administrator must be notified when an error occurs on a server.
An administrator must be able to assign errors to specific administrators for resolution.
Errors that remain unresolved for more than 10 hours must be escalated automatically to another
administrator.
Planned Virtual Machines
The servers in each instance of App1 will be replaced with a set of virtual machines. The planned changes
must meet the following requirements:
Each instance must be redeployed when a new version of App1 is released.
Each instance of App1 must be installed by using the minimum amount of administrative effort.
App2
An application named App2 is hosted on the virtual machines in a Windows Azure public cloud infrastructure.
The performance and availability of the components of App2 must be monitored centrally. Administrators must
be able to modify the configurations of the App2 components.
App3
A service template will be used to deploy multiple instances of a multi-tier application named App3. The vendor
of App3 will provide updates to App3 every two months.
SQL Server Deployment Requirements
VMM administrators plan to deploy many virtual machines that have SQL Server deployed. The administrators
identify the following deployment options for the virtual machines:
The virtual machines will host databases that will be created by using data-tier application (DAC) packages.
The virtual machines will have SQL Server 2008 R2 Standard deployed by using one of six different
configurations.
The operating system for the virtual machines will be either Windows Server 2008 R2 Enterprise or
Windows Server 2008 R2 Standard.

###EndCaseStudy###

You need to recommend a design for the Operations Manager 2012 infrastructure.
What should you include in the recommendation? (More than one answer choice may achieve the goal. Select
the BEST answer.)

What should you include in the recommendation?

###BeginCaseStudy###

Testlet 1
Overview
Trey Research is a consulting company.
Trey Research has three offices. The offices are located in Seattle, Los Angeles, and Toronto.
Trey Research has two data centers. The data centers are located in Los Angeles and Toronto.
Existing Environment
The network contains a single-domain Active Directory forest named treyresearch.com. The network contains
switches that support either SNMPv1 or SNMPv2.
The forest contains 100 physical servers that run Windows Server 2008 R2 Service Pack 1 (SP1). The relevant
servers are configured as shown in the following table.

All of the System Center 2012 servers use Server5 as a database server.
All of the VMM components in the production environment are installed on Server1. Server1 is located in the
Los Angeles data center.
Ten virtual machine hosts are located in the Toronto data center and 90 virtual machine hosts are located in the
Los Angeles data center.
Server9 is used to manage three virtualization hosts in a lab environment.
Requirements
Planned Changes
Trey Research plans to implement the following changes:
Upgrade Server9 to VMM 2012.
Discover and monitor network switches by using Operations Manager.
Grant the network technicians the required permissions to configure the network fabric.
Install a System Center 2012 Service Manager management server on Server7 and a Service Manager data
warehouse management server on Server8.
Provide external access to the Virtual Machine Manager Self-Service Portal (VMMSSP) by using the names
ssp.treyresearch.com and vmm.treyresearch.com.
Private Cloud Infrastructure Requirements
Trey Research identifies the following requirements for the private cloud infrastructure:
Integrate VMM 2012 and Operations Manager 2012.
Ensure that all VMM 2012 components are highly available.Ensure that virtual machines use a MAC address from a custom MAC address pool.
Ensure that Hyper-V hosts can be deployed to bare-metal computers from Server6.
Control the placement of virtual machines based on the performance data gathered by Operations Manager.
Private Cloud Compliance Requirements
Trey Research identifies the following requirements for compliance in the private cloud infrastructure:
Ensure that updates on the Hyper-V hosts can be remediated.
Generate the compliance status of all the servers in the fabric
Ensure that update baselines for all of the servers in the fabric are created.
Private Cloud Services Requirements
Trey Research identifies the following requirements for managing services in the private cloud:
Users in the human resources department must be able to create virtual machines that have two CPUs and
4 GB RAM by using the VMMSSP.
Users in the marketing department must be able to create new virtual machines that will be hosted in the
Toronto office. The virtual machine templates for the marketing department users must be stored in the
Toronto office.

###EndCaseStudy###

You need to recommend changes to Server9 before you upgrade to VMM 2012.
What should you include in the recommendation?

What should you include in the recommendation?

###BeginCaseStudy###

Testlet 1
Overview
Trey Research is a consulting company.
Trey Research has three offices. The offices are located in Seattle, Los Angeles, and Toronto.
Trey Research has two data centers. The data centers are located in Los Angeles and Toronto.
Existing Environment
The network contains a single-domain Active Directory forest named treyresearch.com. The network contains
switches that support either SNMPv1 or SNMPv2.
The forest contains 100 physical servers that run Windows Server 2008 R2 Service Pack 1 (SP1). The relevant
servers are configured as shown in the following table.

All of the System Center 2012 servers use Server5 as a database server.
All of the VMM components in the production environment are installed on Server1. Server1 is located in the
Los Angeles data center.
Ten virtual machine hosts are located in the Toronto data center and 90 virtual machine hosts are located in the
Los Angeles data center.
Server9 is used to manage three virtualization hosts in a lab environment.
Requirements
Planned Changes
Trey Research plans to implement the following changes:
Upgrade Server9 to VMM 2012.
Discover and monitor network switches by using Operations Manager.
Grant the network technicians the required permissions to configure the network fabric.
Install a System Center 2012 Service Manager management server on Server7 and a Service Manager data
warehouse management server on Server8.
Provide external access to the Virtual Machine Manager Self-Service Portal (VMMSSP) by using the names
ssp.treyresearch.com and vmm.treyresearch.com.
Private Cloud Infrastructure Requirements
Trey Research identifies the following requirements for the private cloud infrastructure:
Integrate VMM 2012 and Operations Manager 2012.
Ensure that all VMM 2012 components are highly available.Ensure that virtual machines use a MAC address from a custom MAC address pool.
Ensure that Hyper-V hosts can be deployed to bare-metal computers from Server6.
Control the placement of virtual machines based on the performance data gathered by Operations Manager.
Private Cloud Compliance Requirements
Trey Research identifies the following requirements for compliance in the private cloud infrastructure:
Ensure that updates on the Hyper-V hosts can be remediated.
Generate the compliance status of all the servers in the fabric
Ensure that update baselines for all of the servers in the fabric are created.
Private Cloud Services Requirements
Trey Research identifies the following requirements for managing services in the private cloud:
Users in the human resources department must be able to create virtual machines that have two CPUs and
4 GB RAM by using the VMMSSP.
Users in the marketing department must be able to create new virtual machines that will be hosted in the
Toronto office. The virtual machine templates for the marketing department users must be stored in the
Toronto office.

###EndCaseStudy###

You need to recommend a solution to meet the high-availability requirements for VMM 2012.
What should you include in the recommendation?

You need to implement the planned changes for the VMMSSP

###BeginCaseStudy###

Testlet 1
Overview
Trey Research is a consulting company.
Trey Research has three offices. The offices are located in Seattle, Los Angeles, and Toronto.
Trey Research has two data centers. The data centers are located in Los Angeles and Toronto.
Existing Environment
The network contains a single-domain Active Directory forest named treyresearch.com. The network contains
switches that support either SNMPv1 or SNMPv2.
The forest contains 100 physical servers that run Windows Server 2008 R2 Service Pack 1 (SP1). The relevant
servers are configured as shown in the following table.

All of the System Center 2012 servers use Server5 as a database server.
All of the VMM components in the production environment are installed on Server1. Server1 is located in the
Los Angeles data center.
Ten virtual machine hosts are located in the Toronto data center and 90 virtual machine hosts are located in the
Los Angeles data center.
Server9 is used to manage three virtualization hosts in a lab environment.
Requirements
Planned Changes
Trey Research plans to implement the following changes:
Upgrade Server9 to VMM 2012.
Discover and monitor network switches by using Operations Manager.
Grant the network technicians the required permissions to configure the network fabric.
Install a System Center 2012 Service Manager management server on Server7 and a Service Manager data
warehouse management server on Server8.
Provide external access to the Virtual Machine Manager Self-Service Portal (VMMSSP) by using the names
ssp.treyresearch.com and vmm.treyresearch.com.
Private Cloud Infrastructure Requirements
Trey Research identifies the following requirements for the private cloud infrastructure:
Integrate VMM 2012 and Operations Manager 2012.
Ensure that all VMM 2012 components are highly available.Ensure that virtual machines use a MAC address from a custom MAC address pool.
Ensure that Hyper-V hosts can be deployed to bare-metal computers from Server6.
Control the placement of virtual machines based on the performance data gathered by Operations Manager.
Private Cloud Compliance Requirements
Trey Research identifies the following requirements for compliance in the private cloud infrastructure:
Ensure that updates on the Hyper-V hosts can be remediated.
Generate the compliance status of all the servers in the fabric
Ensure that update baselines for all of the servers in the fabric are created.
Private Cloud Services Requirements
Trey Research identifies the following requirements for managing services in the private cloud:
Users in the human resources department must be able to create virtual machines that have two CPUs and
4 GB RAM by using the VMMSSP.
Users in the marketing department must be able to create new virtual machines that will be hosted in the
Toronto office. The virtual machine templates for the marketing department users must be stored in the
Toronto office.

###EndCaseStudy###

You need to implement the planned changes for the VMMSSP.
What should you do?

What should you recommend deploying to the Toronto data…

###BeginCaseStudy###

Testlet 1
Overview
Trey Research is a consulting company.
Trey Research has three offices. The offices are located in Seattle, Los Angeles, and Toronto.
Trey Research has two data centers. The data centers are located in Los Angeles and Toronto.
Existing Environment
The network contains a single-domain Active Directory forest named treyresearch.com. The network contains
switches that support either SNMPv1 or SNMPv2.
The forest contains 100 physical servers that run Windows Server 2008 R2 Service Pack 1 (SP1). The relevant
servers are configured as shown in the following table.

All of the System Center 2012 servers use Server5 as a database server.
All of the VMM components in the production environment are installed on Server1. Server1 is located in the
Los Angeles data center.
Ten virtual machine hosts are located in the Toronto data center and 90 virtual machine hosts are located in the
Los Angeles data center.
Server9 is used to manage three virtualization hosts in a lab environment.
Requirements
Planned Changes
Trey Research plans to implement the following changes:
Upgrade Server9 to VMM 2012.
Discover and monitor network switches by using Operations Manager.
Grant the network technicians the required permissions to configure the network fabric.
Install a System Center 2012 Service Manager management server on Server7 and a Service Manager data
warehouse management server on Server8.
Provide external access to the Virtual Machine Manager Self-Service Portal (VMMSSP) by using the names
ssp.treyresearch.com and vmm.treyresearch.com.
Private Cloud Infrastructure Requirements
Trey Research identifies the following requirements for the private cloud infrastructure:
Integrate VMM 2012 and Operations Manager 2012.
Ensure that all VMM 2012 components are highly available.Ensure that virtual machines use a MAC address from a custom MAC address pool.
Ensure that Hyper-V hosts can be deployed to bare-metal computers from Server6.
Control the placement of virtual machines based on the performance data gathered by Operations Manager.
Private Cloud Compliance Requirements
Trey Research identifies the following requirements for compliance in the private cloud infrastructure:
Ensure that updates on the Hyper-V hosts can be remediated.
Generate the compliance status of all the servers in the fabric
Ensure that update baselines for all of the servers in the fabric are created.
Private Cloud Services Requirements
Trey Research identifies the following requirements for managing services in the private cloud:
Users in the human resources department must be able to create virtual machines that have two CPUs and
4 GB RAM by using the VMMSSP.
Users in the marketing department must be able to create new virtual machines that will be hosted in the
Toronto office. The virtual machine templates for the marketing department users must be stored in the
Toronto office.

###EndCaseStudy###

You need to recommend a solution to meet the private cloud services requirements for the marketing
department users.
What should you recommend deploying to the Toronto data center?


Page 16 of 21« First...10...1415161718...Last »