What should you do?
You manage several projects. Each project has shared resources and work distribution. You need to ensure that you can adjust the workload for specific resources used across multiple project schedules. What should you do?
What should you do?
You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are created. What should you do?
What should you do?
A section of your project contains only a summary task along with four subtasks and a milestone. You discover that the section is located in the incorrect phase and has the incorrect Work Breakdown Structure (WBS) numbering. You need to move the section to another phase of the project. You also need to ensure that the section reflects the correct WBS numbering. What should you do?
How can you change the Site Theme?
You would like to change the Site Theme of your project workspace. How can you change the Site Theme?
What else needs to be done to make the workflow available in Project Web App (PWA)?
You work as the network administrator at ABC.com. Your responsibilities include maintaining the Project Server 2010 environment. A project manager wants to make a new workflow available in Project Web App (PWA). The project manager has added the workflow in Project Web App (PWA) by selecting Workflow Settings under Site Settings and selecting the Add a Workflow option. However, the workflow is not available in Project Web App (PWA). What else needs to be done to make the workflow available in Project Web App (PWA)?
What attribute must you assign to this resource type?
You work as the Project Manager for company.com Inc. You are using Microsoft Project Web Access to manage your project teams. You would like to create a resource that serves as a model resource for an upcoming electric project. You want the resource to be a “dummy” resource that emulates electricians in the project. You do not want the dummy resource tied to a real account. What attribute must you assign to this resource type?
Which of the following actions will you perform to estimate the costs without assigning specific people to tas
You work as a Project Manager for BlueSoft Inc. You use Microsoft Office Project 2007 for developing the project schedule. You are assigned the project of remodeling a home. Your project will require electricians to work on multiple tasks. You have five electricians to work on your project, but you are not sure who will be the best for a certain task. Which of the following actions will you perform to estimate the costs without assigning specific people to tasks?
What does this figure indicate?
You work as a Project Manager for Tech Perfect Inc. Several projects are running under your supervision. Martha, a team leader of a project, informs you about the performance indexes of her project. The schedule performance index (SPI) of her project is 0.835.
What does this figure indicate?
Which of the following is the most likely cause of the problem?
Tom works as a Project Manager for company.com Inc. The company uses Microsoft Project to schedule a project. Tom has created a resource in his contract-based project. You are also a project manager at the same company as Tom. You will also be using the same contract-based employee for assignments in your project. When you go to assign tasks to the contractor, however, you cannot find the account among the enterprise resources. Which of the following is the most likely cause of the problem?
What type of linking can you use to signal this relationship between projects?
You are the program manager for your organization and you are using Microsoft Project Server and master projects to coordinate all of your projects and subprojects as a program. You have several activities in Project NHQ that must be completed before activities in Project HJH can begin. What type of linking can you use to signal this relationship between projects?