What would you do first?
You need to create a new project schedule by using tasks from an existing project. You need to achieve this goal without inheriting actual hours from the existing project. What would you do first?
What should you do?
All tasks are assigned to multiple team members. A business analyst sends you an e-mail message that contains the dates of her vacation. You need to modify the schedule to reflect delays that are caused only by the business analysts vacation dates. What should you do?
What should you do?
You have team members who work on one of the following shifts: Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to ensure that your project plan accommodates the different shifts. What should you do?
What should you do?
Your project contains many tasks that have dependencies and result in independent networks of tasks. You need to ensure that you can view critical tasks on all independent networks of tasks within the project. What should you do?
Which default view should you use?
You update your project schedule based on information received from your team members in today’s status meeting. You need to compare the current revised project schedule with the baseline schedule side by side. Which default view should you use?
Which two actions should you perform?
Your project contains several baselines. By mistake, you save one of your baselines in Baseline5. You need to move Baseline5 to Baseline3 while preserving the baseline information. You also need to create a new Baseline5 by using today’s data. Which two actions should you perform? Each correct answer presents part of the solution.
What should you do?
You enter the finish date for a task, and then assign a resource. You discover that the task is automatically scheduled for two weeks past the finish date you have entered. You need to identify the problem. What should you do?
Which set of values describes the task?
One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?
What should you do?
The red person icon is displayed next to one of your tasks. You need to find out the reason for the display of the icon. What should you do?
What should you do?
You need to ensure that you can view only the tasks on your projects critical path. What should you do?