PrepAway - Latest Free Exam Questions & Answers

Category: CTAL-TM-UK

Exam CTAL-TM-UK: ISTQB Certified Tester Advanced Level – Test Manager

Which test management control option is most appropriate to adopt under these circumstances?

Topic 4, Scenario 4, V2 “Test Management Tool”
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second Increment
slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the
application with support for manual testing and then to provide a delivery * weeks later to resolve
any remaining points and provide support for automated testing (i.e. the link to the capture-replay
tool).
– Concerns have been expressed by a section of the user community, that in some places the
usability is very poor.
**************************************

Which test management control option is most appropriate to adopt under these circumstances?

which one of the following factors is most likely to lead to a revised view of product risk?

Topic 4, Scenario 4, V2 “Test Management Tool”
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second Increment
slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the
application with support for manual testing and then to provide a delivery * weeks later to resolve
any remaining points and provide support for automated testing (i.e. the link to the capture-replay
tool).
– Concerns have been expressed by a section of the user community, that in some places the
usability is very poor.
**************************************

Risks should be constantly reviewed. Given the current situation, which one of the following
factors is most likely to lead to a revised view of product risk?

Which of the following is least likely to be used as a technique to identify project and product risks?

Topic 4, Scenario 4, V2 “Test Management Tool”
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second Increment
slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the
application with support for manual testing and then to provide a delivery * weeks later to resolve
any remaining points and provide support for automated testing (i.e. the link to the capture-replay
tool).
– Concerns have been expressed by a section of the user community, that in some places the
usability is very poor.
**************************************

Which of the following is least likely to be used as a technique to identify project and product risks?

Which of the following is a project risk mitigation step you might take as test manager?

Topic 4, Scenario 4, V2 “Test Management Tool”
The project situation after 11 months is:
– The first increment was released one week late but contained sufficient functionality to be
declared fit for purpose’. However, there were 20 outstanding incidents deferred to increment two.
– The amount of voluntary overtime worked PV the test team has reduced the second Increment
slippage to just 3 weeks.
– There is talk of reducing the scope of requirements. The purpose of this is to first deliver the
application with support for manual testing and then to provide a delivery * weeks later to resolve
any remaining points and provide support for automated testing (i.e. the link to the capture-replay
tool).
– Concerns have been expressed by a section of the user community, that in some places the
usability is very poor.
**************************************

Which of the following is a project risk mitigation step you might take as test manager?

Which statement best explains how risk can be addressed within the testing strategy?

Topic 5, Scenario 5, V2 “Human Resource System”
For the first increment of the new enterprise HR product you have performed a product risk
analysis using the FMEA method. Five risk items have been identified and the likelihood and
impact have been scored using scoring tables. This has resulted in the following scores:

********************************

You have been asked to write a testing strategy for the company. Which statement best explains
how risk can be addressed within the testing strategy?

Identify THREE main benefits of using systematic test design techniques within this company

Topic 5, Scenario 5, V2 “Human Resource System”
For the first increment of the new enterprise HR product you have performed a product risk
analysis using the FMEA method. Five risk items have been identified and the likelihood and
impact have been scored using scoring tables. This has resulted in the following scores:

********************************

Part of the testing strategy indicates that you are going to be using systematic test design
techniques. Your manager has asked that you present the main advantages of using these
techniques at the next board meeting. Identify THREE main benefits of using systematic test
design techniques within this company.

identify TWO other components of a testing strategy.

Topic 5, Scenario 5, V2 “Human Resource System”
For the first increment of the new enterprise HR product you have performed a product risk
analysis using the FMEA method. Five risk items have been identified and the likelihood and
impact have been scored using scoring tables. This has resulted in the following scores:

********************************

In addition to risk, identify TWO other components of a testing strategy.

What is the Risk Priority Number for risk item number 2?

Topic 5, Scenario 5, V2 “Human Resource System”
For the first increment of the new enterprise HR product you have performed a product risk
analysis using the FMEA method. Five risk items have been identified and the likelihood and
impact have been scored using scoring tables. This has resulted in the following scores:

********************************

What is the Risk Priority Number for risk item number 2?

What would be a test approach regarding the test design techniques to be applied that would fit an item with t

Topic 5, Scenario 5, V2 “Human Resource System”
For the first increment of the new enterprise HR product you have performed a product risk
analysis using the FMEA method. Five risk items have been identified and the likelihood and
impact have been scored using scoring tables. This has resulted in the following scores:

********************************

What would be a test approach regarding the test design techniques to be applied that would fit an
item with the highest risk?

Which of the following is a benefit of independent testing?

Topic 6, Scenario 6, V4 “Independent Test Team”
You have for a while been trying to hire a second test automation specialist for your test team
However, you did not have any luck in finding a suitable candidate. So now, you have been asked
by IT management of XYZ to forward a proposal with alternative solutions for building an
automated regression test suite at system test level over a period of 2 years including needed
training and eventual handover to the test team.
*********************************

Which of the following is a benefit of independent testing?


Page 3 of 712345...Last »