ISC Exam Questions

Which type of risk response is this?

A part of a project deals with the hardware work. As a project manager, you have decided to
hire a company to deal with all hardware work on the project. Which type of risk response is
this?

A.
Mitigation

B.
Exploit

C.
Transference

D.
Avoidance